Category Archives: Sprint-1

Sprint 1 – Retrospective

This week, the first sprint has concluded! And boy, there was a lot to learn and improve upon. For one, within my group, I was the Scrum Master, and it is a bit harder than I anticipated. I had some ideas to organize coming into it already, but sometimes, ideas don’t always meet with reality. At times, things were really effortless, and at others, they were rather difficult.

Some things that worked really well, was the overall organization. As a group, I realized that we were all heading into unknown waters, working with a code base that, though we had some idea of, in reality, we truly had no idea how much of it worked. Because of this uncertainty in many areas, I knew it was crucial to try and share our knowledge with each other as the sprint progressed. Some of the biggest boons, and though it was a bit of luck as well, was splitting our different members into the different portions of our issues.
As an example, we had a cluster of issues in our frontend, backend, and API that dealt with the same thing. Essentially, we had to update/add lots documentation, licenses, etc! This looked very simple at first, but there was some difficulty with clarity, since we simply weren’t familiar with what the specs were. We split three of our members into the three issues, and as we worked on the issues, I made a effort to make sure everyone is keeping each other updated, and this allowed us to realize that despite it being the same issue, we were actually doing things differently from one another. This allowed us to quickly establish what we should do as a group, and from there, we were able to progress forward without additional confusion.

Although things did work well because of our constant sharing of what we learned, not everything went smoothly. Some things that I tried to do as Scrum Master was make sure my group was not overly pressured or crunched for time. In my initial thoughts, I figured that we would have enough ‘brawn’ to sort out the issues with some commitment, and knowing how stressful a time crunch can be, I was very, very lax at times when important issues were being resolved. This relaxed attitude helped with the team morale, but it also did not do much to help with the issues and even stalled some issues. Moving forward, I hope to strike a balance between calming the team when things are not coming to a close, and trying to nudge them forward more when the deadlines are approaching.

As a team, I genuinely believe that we did very well. The biggest flaw in our teamwork, was not actually when we collaborated, but some team members doing things on their own, but these were only very minor issues such as changing issue names without telling anyone, which caused some confusion, as well as encountering a problem and trying to fix it without telling any other group members. Both instances, were very minor at best, and as soon as they were noticed, were stamped out already. Specifically, we know that moving forward, all group members need to try to communicate problems with the team before silently fixing them, and if a issue needs a new name, the new name needs to properly describe what the issue is.

Individually as well, I believe that I was very caught up with making sure that the team functioned, and though that was a great thing, it also negatively impacted my performance as an individual. I oversaw much of the progress, and was kept updated on how various systems worked, so I believe I have a good understanding of how the project works, but I have very little real work to show for it. Moving forward, despite being the Scrum Master, I have to not only manage the group and keep an eye on things, but also use my own abilities to push things forward.

Finally, as much as there was lacking, I believe that moving forward, things will be much smoother. Our group has many great developers, and this was our first time doing a sprint. I already have many ideas on how to improve, and though it might be a bit of trial and error at times, we as a team, have all the ability to clear out our issues!

From the blog CS@Worcester – Bored Coding by iisbor and used with permission of the author. All other rights reserved by the author.

Sprint-1

Hi, and welcome to the Sprint Retrospective Blog. I have completed these tasks on GitLab for the group project; the team and I have been assigned to decide whether to implement these changes when necessary. For myself, I have done there is one activity that does require modifications, while the other three do not. These ISSUES weight totals are reasonable and easy to do once getting to the mindset of the work and practice.

 The Issues:

My challenge concerning these works is that I took the time to review the codes, and everything seems to be great, so it does not require any modification. Even if it means setting aside some time so that you can go to the next activity or task in the sequence. On the other side, it makes it appear that all I have done is read the codes and determine that there is no need to update them, making me feel bad because I haven’t worked as hard as I should have been working on this project. To improve myself as an individual to have goals that include conquering negative emotions, recognizing that the quality of the job has been maintained, and making additional recommendations to the team regarding acceptable actions. In the upcoming year, is to improve my time management abilities and all of these measurements so that I can finish all of my work within the assigned time window. I need to improve my technical skills and knowledge to contribute to the team significantly.
 

The team and I had a rough start in completing all the tasks on the sprint backlog; we encountered some challenges along the way. We faced several technological challenges during the development process, leading to delays. Additionally, some communication breakdowns led to misunderstandings and duplication of efforts. To improve on those issues by strengthening our technical skills and knowledge. This work can be achieved through regular training and knowledge-sharing sessions. We also need to establish better communication channels to ensure that everyone is on the same page and that there are no misunderstandings. Additionally, we need better tracking and monitoring mechanisms to ensure we are on track with our goals.

In conclusion, our team had a rough start, but we got through a lot of success during the first sprint. We overcame some of the obstacles while working through the sprint backlog and completing some of the assignments.
 

From the blog Andrew Lam’s little blog by Andrew Lam and used with permission of the author. All other rights reserved by the author.

Sprint-1

Hi, and welcome to the Sprint Retrospective Blog. I have completed these tasks on GitLab for the group project; the team and I have been assigned to decide whether to implement these changes when necessary. For myself, I have done there is one activity that does require modifications, while the other three do not. These ISSUES weight totals are reasonable and easy to do once getting to the mindset of the work and practice.

 The Issues:

My challenge concerning these works is that I took the time to review the codes, and everything seems to be great, so it does not require any modification. Even if it means setting aside some time so that you can go to the next activity or task in the sequence. On the other side, it makes it appear that all I have done is read the codes and determine that there is no need to update them, making me feel bad because I haven’t worked as hard as I should have been working on this project. To improve myself as an individual to have goals that include conquering negative emotions, recognizing that the quality of the job has been maintained, and making additional recommendations to the team regarding acceptable actions. In the upcoming year, is to improve my time management abilities and all of these measurements so that I can finish all of my work within the assigned time window. I need to improve my technical skills and knowledge to contribute to the team significantly.
 

The team and I had a rough start in completing all the tasks on the sprint backlog; we encountered some challenges along the way. We faced several technological challenges during the development process, leading to delays. Additionally, some communication breakdowns led to misunderstandings and duplication of efforts. To improve on those issues by strengthening our technical skills and knowledge. This work can be achieved through regular training and knowledge-sharing sessions. We also need to establish better communication channels to ensure that everyone is on the same page and that there are no misunderstandings. Additionally, we need better tracking and monitoring mechanisms to ensure we are on track with our goals.

In conclusion, our team had a rough start, but we got through a lot of success during the first sprint. We overcame some of the obstacles while working through the sprint backlog and completing some of the assignments.
 

From the blog Andrew Lam’s little blog by Andrew Lam and used with permission of the author. All other rights reserved by the author.

Sprint-1

Hi, and welcome to the Sprint Retrospective Blog. I have completed these tasks on GitLab for the group project; the team and I have been assigned to decide whether to implement these changes when necessary. For myself, I have done there is one activity that does require modifications, while the other three do not. These ISSUES weight totals are reasonable and easy to do once getting to the mindset of the work and practice.

 The Issues:

My challenge concerning these works is that I took the time to review the codes, and everything seems to be great, so it does not require any modification. Even if it means setting aside some time so that you can go to the next activity or task in the sequence. On the other side, it makes it appear that all I have done is read the codes and determine that there is no need to update them, making me feel bad because I haven’t worked as hard as I should have been working on this project. To improve myself as an individual to have goals that include conquering negative emotions, recognizing that the quality of the job has been maintained, and making additional recommendations to the team regarding acceptable actions. In the upcoming year, is to improve my time management abilities and all of these measurements so that I can finish all of my work within the assigned time window. I need to improve my technical skills and knowledge to contribute to the team significantly.
 

The team and I had a rough start in completing all the tasks on the sprint backlog; we encountered some challenges along the way. We faced several technological challenges during the development process, leading to delays. Additionally, some communication breakdowns led to misunderstandings and duplication of efforts. To improve on those issues by strengthening our technical skills and knowledge. This work can be achieved through regular training and knowledge-sharing sessions. We also need to establish better communication channels to ensure that everyone is on the same page and that there are no misunderstandings. Additionally, we need better tracking and monitoring mechanisms to ensure we are on track with our goals.

In conclusion, our team had a rough start, but we got through a lot of success during the first sprint. We overcame some of the obstacles while working through the sprint backlog and completing some of the assignments.
 

From the blog Andrew Lam’s little blog by Andrew Lam and used with permission of the author. All other rights reserved by the author.

Sprint-1

Hi, and welcome to the Sprint Retrospective Blog. I have completed these tasks on GitLab for the group project; the team and I have been assigned to decide whether to implement these changes when necessary. For myself, I have done there is one activity that does require modifications, while the other three do not. These ISSUES weight totals are reasonable and easy to do once getting to the mindset of the work and practice.

 The Issues:

My challenge concerning these works is that I took the time to review the codes, and everything seems to be great, so it does not require any modification. Even if it means setting aside some time so that you can go to the next activity or task in the sequence. On the other side, it makes it appear that all I have done is read the codes and determine that there is no need to update them, making me feel bad because I haven’t worked as hard as I should have been working on this project. To improve myself as an individual to have goals that include conquering negative emotions, recognizing that the quality of the job has been maintained, and making additional recommendations to the team regarding acceptable actions. In the upcoming year, is to improve my time management abilities and all of these measurements so that I can finish all of my work within the assigned time window. I need to improve my technical skills and knowledge to contribute to the team significantly.
 

The team and I had a rough start in completing all the tasks on the sprint backlog; we encountered some challenges along the way. We faced several technological challenges during the development process, leading to delays. Additionally, some communication breakdowns led to misunderstandings and duplication of efforts. To improve on those issues by strengthening our technical skills and knowledge. This work can be achieved through regular training and knowledge-sharing sessions. We also need to establish better communication channels to ensure that everyone is on the same page and that there are no misunderstandings. Additionally, we need better tracking and monitoring mechanisms to ensure we are on track with our goals.

In conclusion, our team had a rough start, but we got through a lot of success during the first sprint. We overcame some of the obstacles while working through the sprint backlog and completing some of the assignments.
 

From the blog Andrew Lam’s little blog by Andrew Lam and used with permission of the author. All other rights reserved by the author.

Sprint-1

Hi, and welcome to the Sprint Retrospective Blog. I have completed these tasks on GitLab for the group project; the team and I have been assigned to decide whether to implement these changes when necessary. For myself, I have done there is one activity that does require modifications, while the other three do not. These ISSUES weight totals are reasonable and easy to do once getting to the mindset of the work and practice.

 The Issues:

My challenge concerning these works is that I took the time to review the codes, and everything seems to be great, so it does not require any modification. Even if it means setting aside some time so that you can go to the next activity or task in the sequence. On the other side, it makes it appear that all I have done is read the codes and determine that there is no need to update them, making me feel bad because I haven’t worked as hard as I should have been working on this project. To improve myself as an individual to have goals that include conquering negative emotions, recognizing that the quality of the job has been maintained, and making additional recommendations to the team regarding acceptable actions. In the upcoming year, is to improve my time management abilities and all of these measurements so that I can finish all of my work within the assigned time window. I need to improve my technical skills and knowledge to contribute to the team significantly.
 

The team and I had a rough start in completing all the tasks on the sprint backlog; we encountered some challenges along the way. We faced several technological challenges during the development process, leading to delays. Additionally, some communication breakdowns led to misunderstandings and duplication of efforts. To improve on those issues by strengthening our technical skills and knowledge. This work can be achieved through regular training and knowledge-sharing sessions. We also need to establish better communication channels to ensure that everyone is on the same page and that there are no misunderstandings. Additionally, we need better tracking and monitoring mechanisms to ensure we are on track with our goals.

In conclusion, our team had a rough start, but we got through a lot of success during the first sprint. We overcame some of the obstacles while working through the sprint backlog and completing some of the assignments.
 

From the blog Andrew Lam’s little blog by Andrew Lam and used with permission of the author. All other rights reserved by the author.

Sprint-1

Hi, and welcome to the Sprint Retrospective Blog. I have completed these tasks on GitLab for the group project; the team and I have been assigned to decide whether to implement these changes when necessary. For myself, I have done there is one activity that does require modifications, while the other three do not. These ISSUES weight totals are reasonable and easy to do once getting to the mindset of the work and practice.

 The Issues:

My challenge concerning these works is that I took the time to review the codes, and everything seems to be great, so it does not require any modification. Even if it means setting aside some time so that you can go to the next activity or task in the sequence. On the other side, it makes it appear that all I have done is read the codes and determine that there is no need to update them, making me feel bad because I haven’t worked as hard as I should have been working on this project. To improve myself as an individual to have goals that include conquering negative emotions, recognizing that the quality of the job has been maintained, and making additional recommendations to the team regarding acceptable actions. In the upcoming year, is to improve my time management abilities and all of these measurements so that I can finish all of my work within the assigned time window. I need to improve my technical skills and knowledge to contribute to the team significantly.
 

The team and I had a rough start in completing all the tasks on the sprint backlog; we encountered some challenges along the way. We faced several technological challenges during the development process, leading to delays. Additionally, some communication breakdowns led to misunderstandings and duplication of efforts. To improve on those issues by strengthening our technical skills and knowledge. This work can be achieved through regular training and knowledge-sharing sessions. We also need to establish better communication channels to ensure that everyone is on the same page and that there are no misunderstandings. Additionally, we need better tracking and monitoring mechanisms to ensure we are on track with our goals.

In conclusion, our team had a rough start, but we got through a lot of success during the first sprint. We overcame some of the obstacles while working through the sprint backlog and completing some of the assignments.
 

From the blog Andrew Lam’s little blog by Andrew Lam and used with permission of the author. All other rights reserved by the author.

Sprint-1

Hi, and welcome to the Sprint Retrospective Blog. I have completed these tasks on GitLab for the group project; the team and I have been assigned to decide whether to implement these changes when necessary. For myself, I have done there is one activity that does require modifications, while the other three do not. These ISSUES weight totals are reasonable and easy to do once getting to the mindset of the work and practice.

 The Issues:

My challenge concerning these works is that I took the time to review the codes, and everything seems to be great, so it does not require any modification. Even if it means setting aside some time so that you can go to the next activity or task in the sequence. On the other side, it makes it appear that all I have done is read the codes and determine that there is no need to update them, making me feel bad because I haven’t worked as hard as I should have been working on this project. To improve myself as an individual to have goals that include conquering negative emotions, recognizing that the quality of the job has been maintained, and making additional recommendations to the team regarding acceptable actions. In the upcoming year, is to improve my time management abilities and all of these measurements so that I can finish all of my work within the assigned time window. I need to improve my technical skills and knowledge to contribute to the team significantly.
 

The team and I had a rough start in completing all the tasks on the sprint backlog; we encountered some challenges along the way. We faced several technological challenges during the development process, leading to delays. Additionally, some communication breakdowns led to misunderstandings and duplication of efforts. To improve on those issues by strengthening our technical skills and knowledge. This work can be achieved through regular training and knowledge-sharing sessions. We also need to establish better communication channels to ensure that everyone is on the same page and that there are no misunderstandings. Additionally, we need better tracking and monitoring mechanisms to ensure we are on track with our goals.

In conclusion, our team had a rough start, but we got through a lot of success during the first sprint. We overcame some of the obstacles while working through the sprint backlog and completing some of the assignments.
 

From the blog Andrew Lam’s little blog by Andrew Lam and used with permission of the author. All other rights reserved by the author.

Sprint-1

Hi, and welcome to the Sprint Retrospective Blog. I have completed these tasks on GitLab for the group project; the team and I have been assigned to decide whether to implement these changes when necessary. For myself, I have done there is one activity that does require modifications, while the other three do not. These ISSUES weight totals are reasonable and easy to do once getting to the mindset of the work and practice.

 The Issues:

My challenge concerning these works is that I took the time to review the codes, and everything seems to be great, so it does not require any modification. Even if it means setting aside some time so that you can go to the next activity or task in the sequence. On the other side, it makes it appear that all I have done is read the codes and determine that there is no need to update them, making me feel bad because I haven’t worked as hard as I should have been working on this project. To improve myself as an individual to have goals that include conquering negative emotions, recognizing that the quality of the job has been maintained, and making additional recommendations to the team regarding acceptable actions. In the upcoming year, is to improve my time management abilities and all of these measurements so that I can finish all of my work within the assigned time window. I need to improve my technical skills and knowledge to contribute to the team significantly.
 

The team and I had a rough start in completing all the tasks on the sprint backlog; we encountered some challenges along the way. We faced several technological challenges during the development process, leading to delays. Additionally, some communication breakdowns led to misunderstandings and duplication of efforts. To improve on those issues by strengthening our technical skills and knowledge. This work can be achieved through regular training and knowledge-sharing sessions. We also need to establish better communication channels to ensure that everyone is on the same page and that there are no misunderstandings. Additionally, we need better tracking and monitoring mechanisms to ensure we are on track with our goals.

In conclusion, our team had a rough start, but we got through a lot of success during the first sprint. We overcame some of the obstacles while working through the sprint backlog and completing some of the assignments.
 

From the blog Andrew Lam’s little blog by Andrew Lam and used with permission of the author. All other rights reserved by the author.

Sprint-1

Hi, and welcome to the Sprint Retrospective Blog. I have completed these tasks on GitLab for the group project; the team and I have been assigned to decide whether to implement these changes when necessary. For myself, I have done there is one activity that does require modifications, while the other three do not. These ISSUES weight totals are reasonable and easy to do once getting to the mindset of the work and practice.

 The Issues:

My challenge concerning these works is that I took the time to review the codes, and everything seems to be great, so it does not require any modification. Even if it means setting aside some time so that you can go to the next activity or task in the sequence. On the other side, it makes it appear that all I have done is read the codes and determine that there is no need to update them, making me feel bad because I haven’t worked as hard as I should have been working on this project. To improve myself as an individual to have goals that include conquering negative emotions, recognizing that the quality of the job has been maintained, and making additional recommendations to the team regarding acceptable actions. In the upcoming year, is to improve my time management abilities and all of these measurements so that I can finish all of my work within the assigned time window. I need to improve my technical skills and knowledge to contribute to the team significantly.
 

The team and I had a rough start in completing all the tasks on the sprint backlog; we encountered some challenges along the way. We faced several technological challenges during the development process, leading to delays. Additionally, some communication breakdowns led to misunderstandings and duplication of efforts. To improve on those issues by strengthening our technical skills and knowledge. This work can be achieved through regular training and knowledge-sharing sessions. We also need to establish better communication channels to ensure that everyone is on the same page and that there are no misunderstandings. Additionally, we need better tracking and monitoring mechanisms to ensure we are on track with our goals.

In conclusion, our team had a rough start, but we got through a lot of success during the first sprint. We overcame some of the obstacles while working through the sprint backlog and completing some of the assignments.
 

From the blog Andrew Lam’s little blog by Andrew Lam and used with permission of the author. All other rights reserved by the author.